Six months more

Yesterday I broke the news to Big T that it would probably take us another six months to get things finished. And that’s if we don’t run out of money.

It’s hard to explain why it’s taking us so long except that really we only started work in September. It took eight months to get approval to take the wall down.

Before we have a kitchen, we need to do the plumbing, electrics, move the boiler, replace the French doors, plaster the walls and install a floor.

And so it won’t be before Christmas and we’ll be lucky to get it done by Big T’s birthday in early February.

Better to be realistic!